Megastar Cineplex - Hung Vuong Plaza HSBC Etown Indochina Plaza Ha Noi (IPH) - Vietnam California Wow Xperience Microsoft Office Fit-Out Laguna Lang Co Resort Six Senses Con Dao Resort Procter & Gamble Office FV Clinic Bitexco Financial Tower Hog’s Breath Restaurant Starbucks Coffee Sheraton Nha Trang HSBC Phu My Hung Branch Microsoft Hanoi Office Australian Consulate General, Ho Chi Minh City, Vietnam Chateau Clubhouse S8 Mipec Riverside Mock Up Unit Bitexco Financial Tower Nam Hai Resort Le Gia Trang Villa

How is the project schedule affected if we use imported goods instead of products available in local markets ?

(11:26:24 AM - 06/05/2014)
    How is the project schedule affected if we use imported goods instead of products available in local markets ?
     
    How is the project schedule affected if we use imported goods instead of products available in local markets ?
    We often use local products for projects that have short timeframes, such as 3-4 weeks for each project. For the projects with flexible schedules, see the times below help make the choice between imported or local goods. 

    Arrival time for some products :
    1. Carpet: 5-7 weeks (import from Thailand).

     2. Chairs, sofas, tables: 8-10 weeks (from Europe), and 4-5 week (from Asia).

     3. International-standard fire-resistant doors: 5-6 weeks (from Asia).

     4. Hardware: 8-10 weeks (from Japan, USA, Germany).

     5. Ceiling tile and frames: 10-12 weeks (from USA).

     6. Some kinds of Vinyl: 4-5 weeks (from China).

     

     

     